A software company sets up m number of computer system to finish an assignment in 17 days. If 4 computer systems crashed on the start of the second day 4 more computer systems crashed on the start of the third day and so on, then it took 8 more days to finish the assignment The value of is equal to
- (A)125
- (B)180
- (C)160
- (D)150✓ Correct
Answer: (D)
Solution
The job originally needs machines for days, i.e. machine-days of work, and actually finishes in days with machines running on day (). Equating total work: